Published Saturday 15 August 2026. Norbury residents who drive, take buses, use taxis or make deliveries through Streatham Hill should check Transport for London’s latest A23 works advice before travelling north this month.
This is a practical follow-up to the Gazette’s June report on the A23 Streatham Hill improvement works. TfL’s current works page now lists specific August overnight closure dates for resurfacing, alongside continuing lane restrictions and temporary traffic signals.
Overnight closure dates listed by TfL
TfL says overnight closures on Streatham Hill for resurfacing works are scheduled between 21:00 and 05:30 on the following dates:
- Sunday 9 August to Wednesday 12 August 2026: northbound
- Thursday 13 August 2026: southbound
- Sunday 16 August to Wednesday 19 August 2026: southbound
- Sunday 23 August 2026: southbound
Residents should check TfL’s page before setting off, as roadworks and diversions can change at short notice.
Why it matters for Norbury
The works are north of Norbury, but the A23 is a common route for journeys towards Streatham, Brixton and central London. Delays or overnight diversions around Streatham Hill may affect car, taxi, delivery and some bus journeys from the Norbury area.
TfL also says there are lane restrictions in both directions between the junction with Sternhold Avenue on Streatham Hill and the junction with Holmewood Road on Brixton Hill. Temporary traffic signals are listed until 1 September, and again from Monday 28 September until late 2026.
Practical checks before travelling
- If your journey uses the A23 through Streatham Hill overnight, check the latest TfL advice and allow extra time.
- If you are travelling north from Norbury and do not need to stop in Streatham or Brixton, compare alternative routes before setting off.
- If using buses through Streatham, check live bus status and any notices at stops, especially during overnight closure periods.
- If walking or cycling near the works area, follow signed local diversions rather than assuming the usual route is open.
Official links
TfL says the wider A23 Streatham Hill project is due to finish in spring 2027 and is intended to provide a new permanent road layout with protected cycle lanes and dedicated bus lanes in both directions.
For the latest information, use TfL’s A23 Streatham Hill works page, TfL bus status updates and TfL traffic status updates.